Cover Story
Automatic Sprinkler Systems: Commissioning vs. Acceptance Testing
by Scott Martorano, CFPS
August 1, 2008
Although sometimes used interchangeably, these terms are distinct. Understanding each one will help ensure that a building’s fire protection features operate as designed.
Since the early 1980s, automatic sprinkler
systems have gradually increased in complexity. Advances in sprinkler
technology have lead to the development of extended coverage, residential,
quick-response and ESFR sprinklers, to name a few. The most common sprinkler
system to be installed is still the basic wet pipe system. However, dry
systems, preaction, deluge and foam water sprinkler systems have seen steady
growth as well.
All of these systems must be put through acceptance testing by the installing
contractor to ensure proper operation, but individual acceptance testing may
not verify interconnections and operation with other building fire protection
systems. In buildings where the sprinkler systems are intended to work with other
fire protection systems — such as fire alarm systems or smoke- control systems
— a more complete commissioning program may be the more appropriate method to
ensure the owner’s expectations are met.
While advances in technology have greatly improved fire-protection-system
capabilities, the individual system components and related building designs
have become more complex. This has resulted in more-demanding acceptance
testing, a more-challenging installation process, and, in some cases, difficult
long-term system maintenance for many sprinkler systems. This can be especially
true if the sprinkler system requires interconnection and operation with other
fire protection systems.
Many times in newly constructed buildings, automatic sprinkler systems are
treated as autonomous within the structure’s overall fire protection scheme
during the design, construction and long-term operation. In some cases, the
building owner may consider this acceptable. In other cases, the building owner
may seek assurance that the building’s fire protection features work together
as intended when the building was designed.

Flow control sprinkler system. All photos courtesy of Viking Corp.
Within the fire protection industry, confusion
exists between the terms “commissioning” and “acceptance testing,” and, in some
cases, the terms are thought of as interchangeable. This is not the case. A
distinction needs to be made between the two terms to help ensure that the
individual fire protection systems — in this case, the automatic sprinkler
system — receive the proper acceptance testing, and, if desired, a separate
building commissioning process can be completed.
To help define and clarify what is involved in the commissioning process, the
National Fire Protection Association (NFPA) has embarked on a project to
develop a new document entitled,
NFPA 3 — Commissioning Fire
Protection Systems to clarify and describe the building commissioning
process for the fire protection features. The acceptance testing for the
individual sprinkler system will be found with
NFPA 13 —Standard for
Installation for Sprinkler Systems.
Sprinkler System Acceptance Testing

Wet pipe system.
To complete the installation of a sprinkler
system, the installing contractor must complete the acceptance steps required
in NFPA 13: “These final steps in the design and installation of sprinkler
systems are to confirm that the basic requirements of NFPA 13 are satisfied,
that the work was completed in an acceptable manner, and that the customer is
receiving a system that performs as intended.”1
The contractor must notify the Authority Having Jurisdiction, who will then
decide if they wish to witness the testing or not. The contractor then conducts
the individual system acceptance and operational testing described in NFPA 13.
The specific item tested will vary depending on what type of sprinkler system
is installed, but may include all or some of the following:
1. Flushing the underground pipe.
2. Hydrostatic test.
3. The air test for dry systems (non-interlock preaction or double interlock
preaction systems).
4. The system operational test.
5. Submitting the contractor’s material and test
certificate.
Typically, the sprinkler contractor will be contractually obligated to perform
acceptance testing only on the sprinkler systems they install. Testing the
interface between systems to ensure that the building’s overall fire protection
scheme has been achieved and the fire protection systems work together is
commonly overlooked in the construction documents. Coordinating all the trades
and testing at the same time can be extremely difficult under the best
circumstances
Sprinkler Systems as Part of a Commissioning Process

Integrated preaction system.
Today more property owners are requesting that
their sprinkler systems be commissioned as part of “a quality assurance or
quality control process that will verify the fire protection systems perform
together as intended.”2 Too many buildings have systems that do not work
properly due to any number of reasons; poor initial design, poor installation,
inadequate testing, no owner’s manual and no trained personnel, unfortunately,
are not uncommon problems. These and other problems are driving the
establishment of the comprehensive commissioning program for the building fire
protection systems that is being developed in
NFPA 3 —Commissioning
Fire Protection Systems.
What differentiates commissioning from acceptance testing? The commissioning of
a sprinkler system involves more than the acceptance testing described within
NFPA 13. “Commissioning begins at project inception and continues through
design, construction and project closeout and then throughout the facility’s
operation.”3 Commissioning can be defined as “a systematic process that
provides documented confirmation that fire and life safety systems function
according to the intended design criteria set forth in the project documents
and satisfy the owner’s operational needs.”
“NFPA statistics indicate that sprinkler systems function exceptionally well
when properly maintained. The few instances of system failure are found to be
directly related to shut water-supply control valves and inadequate
maintenance, which can be construed as a misunderstanding of the operational
needs of the system.”4

Multiple sprinkler system risers.
The object of commissioning is to:
1. Clearly document the building owner’s needs.
2. Provide an organized, documented approach to verify quality of
deliverables.
3. Verify through documentation that systems and equipment perform according to
specification and the building owner’s needs.
4. Provide improved training of maintenance personnel.
5. Provide for improved documentation of operation and maintenance requirements
for systems and equipment.5
If the property owner requests a complete commissioning program, consideration
should be given to adding specific language to the construction documents that
identifies key areas of interface between systems. The basis for the design
should include the owner’s expectations for how all fire protection and life
safety systems will work together.
Specific language should be considered for all system interconnections to
ensure compatibility and operation. Responsibility for testing during the
construction phase of the project needs to be clearly identified, and language
requiring specific testing of interconnections should be considered.
Conclusion

High expansion foam acceptance test.
Acceptance testing and a commissioning program
are two very different things. Not all buildings may require the more complete
commissioning process. However, where complex interconnections and multiple
fire protection systems are installed (in addition to the sprinkler system),
consideration should be given to taking a step beyond the standard sprinkler
system acceptance testing.
Sprinkler systems and fire protection systems as a whole will continue to
increase in complexity. Ensuring the building’s fire protection features
operate as designed may not be limited to individual systems any longer.
References
1 Dubay, C., Automatic Sprinkler
Systems Handbook, 2007 Edition, National Fire Protection Association,
1 Batterymarch Park, Quincy, MA , 2007, pg 857
2 Hague, D., Commissioning Fire Protection Systems, National
Fire Protection Association, 1 Batterymarch Park, Quincy, MA , 2005, page 1
3 Hague, D., Commissioning Fire Protection Systems, page 1
4 Hague, D., Commissioning Fire Protection Systems, page 49
5 Hague, D., Commissioning Fire Protection Systems, page 2
Scott Martorano, CFPS
Scott Martorano, CFPS, is the senior manager of technical services for The Viking Corp. He is a member of several NFPA technical committees and has 18 years’ fire protection industry experience in installation and design of special hazard and sprinkler systems. In addition, he is a part time instructor in fire protection design for the State University of New York. For more information, contact Viking Corp. at (800) 968-9501, or visit www.vikinggroupinc.com.
Did you enjoy this article? Click here to subscribe to the magazine.
CONNECT WITH PM ENGINEER: