Ask The Expert — January 2010
January 1, 2010
Providing answers to your plumbing, piping, fire protection and hydronics questions.
A Quick Fix For CPVC Installation
Max Gandy [max@g3designbuild.com]
writes:
I have an above-ground installation with 6” CPVC pipe, 140ºF and about 100
psi. One of the 45-degree elbows is leaking and needs to be replaced. This
installation is critical and needs minimum replacement time. I’m considering
pre-gluing a new section with a 45 installed, then cutting the old one out and
installing the new using mechanical compression joint couplers. In
addition, I’m thinking about installing pipe clamps on either side of the
mechanical joint with all thread rods connecting in order to keep the pipe in
the compression coupler. We’re hoping the mechanical fix will only cause the
building to be down for a few hours. Is this the quickest fix? What are your
thoughts?
Julius Ballanco, P.E., CPD, F-ASPE, responds:
Yes, this type of repair will work, plus it would meet the code. However,
the manufacturers will tell you that the best joint for a CPVC installation is
a solvent cement joint. While you may not have time for the solvent cement to
set up, it still would be best for this type of repair.
Flow Reduction to Water Meter
Tim Keinath
[timak@tds.net] writes:
There is a 3” water line feeding a
school with a 1-1/2” meter. How much is flow reduced? I’m not sure
how to determine this.
Julius Ballanco responds:
Flow is reduced quite a bit. It is very unusual to see that much of a
reduction between the water service (outside/underground) and the water meter.
The way to find out the restriction in flow is to check the water meter manufacturer’s
Web site and download their data sheets. The data sheets have a flow curve that
shows the pressure loss through the meter at given flows. The data sheet will
also let you know where the meter tops out as the maximum flow through the
meter.
PVC Leak Testing
J.R. Anderson, P.E.,
LEED-AP, Anderson Engineering, Germantown, TN, writes:
The architect on a project that I am the commissioning authority for
has requested an interpretation of doing a more stringent leak test based on cycling
the 24-hour pressure testing. The project is a school that is going to be
the first in the area (and maybe the country) that will be a chilled beam project. The
contractors want to use the traditional copper, but PVC is an option that works,
and the architect is holding his ground. I have not done any research yet
but thought this would be another approach.
Julius Ballanco responds:
The cycling pressure test for a field installation serves no
useful purpose. Please understand that certain piping materials and
fitting systems go through a thermocycling test to be qualified for listing
purposes. The purpose of the pressure test in the field is to determine if
there are any leaks in the piping system. It is not to qualify the pipe or the
fittings. Therefore, a cycle test is inappropriate.
The design and specification prepared by the engineer (or architect) should
take into account the proper piping materials for the installation based on
their listing. This would include thermocycling tests when required for
listing. I hope this assists you.
In Search of CAD Details
Stanley Brachowski
[stanbrachowski@delren.com] writes:
I am looking for two
hydronic-related details in CAD. Specifically, dual-boiler control with temperature
from an outside-located thermostat; and a typical piping layout of under-floor
heating, with circulating pumps connected. Really hope you can help
me.
John Siegenthaler, P.E., responds:
This is too broad of a description to get you something that might be of
assistance. You might want to consider the schematics in the textbook Modern
Hydronic Heating (2nd edition), or
consider purchasing the Radiant Precision book available at www.hydronicpros.com and www.aecstore.com. Both
references cover all of the information you are seeking.
|